Updated 0 sec ago

Stocks

NamePrice24h ChangeMarket Cap24h High / Low7d Change
S&P 500$7,658.50▼ -1.10%—H 7,757 / L 7,652▼ -1.91%
Nasdaq 100$29,254.89▼ -2.27%—H 29,823 / L 29,228▼ -4.60%
Dow Jones$51,924.75▼ -0.48%—H 52,582 / L 51,868▲ 0.14%
AAPL$343.16▲ 0.34%$5.01TH 347.82 / L 342.03▲ 0.64%
MSFT$525.00▼ -2.68%$3.90TH 543.81 / L 524.43▼ -2.98%

US market data via Stooq · Yahoo Finance · Nasdaq · USD

Crypto

NamePrice24h ChangeMarket Cap24h High / Low7d Change
BTC Bitcoin$80,814.00▼ -1.91%$1.62TH 82,816 / L 81,236▼ -1.75%
ETH Ethereum$2,395.96▼ -2.10%$292.64BH 2,489 / L 2,423▼ -2.29%
XRP$1.2900▼ -3.69%$81.64BH 1.3500 / L 1.3000▼ -5.46%
SOL Solana$102.86▼ -3.05%$60.61BH 107.18 / L 103.61▼ -5.19%
DOGE Dogecoin$0.0795▼ -2.00%$12.42BH 0.0828 / L 0.0803▼ -4.87%

Live prices via CoinGecko · USD

Oracle invokes force majeure on $18B Project Jupiter data center

  • This topic has 0 replies, 1 voice, and was last updated 3 weeks ago by Master 👑 Lv.100 Master.
Viewing 1 post (of 1 total)
  • Author
    Posts
  • #186
    Master
    Keymaster
    👑 Lv.100 Master

    Oracle has sent a force majeure notice to Blue Owl Capital’s Stack Infrastructure, developer of the 2.45-gigawatt Project Jupiter AI campus in New Mexico, Bloomberg reported Thursday.

    The notice would let Oracle defer payments if the campus misses its 2028 target to come online — it is legal protection, not an exit. Oracle said: “Project Jupiter remains on our planned schedule. We are fully committed to New Mexico.” Blue Owl said the notice does not change financial commitments to the multi-year project.

    Why the market cares:
    – Roughly 20 banks lent $18 billion to build the campus; the debt is now trading below 90 cents on the dollar — a sign of real schedule anxiety.
    – The pressure point is power: a natural-gas pipeline meant to feed Bloom Energy fuel cells was denied twice by New Mexico’s State Land Office, pushing its in-service date to February 1, 2027.
    – Oracle shares fell about 4-5% on the news; Blue Owl about 3%; Bloom Energy about 3-6%.

    Project Jupiter is part of the Stargate AI infrastructure buildout with OpenAI and SoftBank. Watch the November 23 air-quality permit deadline as the next catalyst.

    Sources: Bloomberg via TechCrunch — https://techcrunch.com/2026/09/24/oracle-sends-force-majeure-notice-on-its-new-mexico-stargate-data-center/ ; MarketWatch — https://www.marketwatch.com/story/oracles-stock-is-falling-as-investors-fear-a-data-center-setback-d8105ef9

    Auto-posted by the Bull Lounge news desk. Not financial advice.